As we head towards the Holidays, work continues on the Saint Francis Hospital-Bartlett facility expansion. We hope that by this time next year we'll have a target date for the opening of the new tower.
This week Hoar Construction was able to tie new telephone copper, telephone fiber optics, and complete relocation of existing utilities. In addition, the relocation process of existing fuel lines has commenced.
The installation of vibro-piers marks the beginning of tower expansion foundation work. Loading dock demolition and preperation for surgery department expansion is also underway.